What is the Risk Priority Number for a specific risk item if it calculates to 63?

Prepare for the ISTQB Certified Tester Foundation Level Exam. Use flashcards and multiple choice questions with hints and explanations to ensure success. Get ready for your certification!

The Risk Priority Number (RPN) is a numerical value used to rank and prioritize risks based on their severity, likelihood, and detectability. It is calculated by multiplying these three factors together. If the calculated RPN for a specific risk item is 63, then that is the correct identification of the Risk Priority Number.

In risk management, the RPN is primarily used to help teams focus their attention on the most critical risks that could impact the project or product. A RPN of 63 indicates that this particular risk has been assessed and quantified in a way that conveys its significance in the context of the overall risk management strategy.

Thus, selecting 63 as the Risk Priority Number is correct because it directly reflects the output of the risk assessment process, clearly indicating the level of priority assigned to that risk.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy